DoD Changes Earned Value Management Requirements

The Department of Defense has issued changed clauses to the Defense Acquisition Regulations System (DFARS) concerning required contractor use of Earned Value Management (EVM) on federal projects. Under this change, which has been in the works for some time, contractors are no longer required to submit cost/schedule status reports (CS/SR) in programs using EVM. In addition, the thresholds for the required use of EVM in Defense programs are based on the value of the program and the type of contract, as summarized in this table:

Table shows no use of EVM for FFP contracts . For Cost-plus and award fee contract, EVM is not required for projects less than $20 million.

Here’s the link to the full text of the changed EVM clauses.


Comments

The comment input form below supports HTML formatting.  If you want to use any of the usual kinds of text formatting, just highlight the text you're formatting and then hit one of the standard formatting buttons that are just above the Subject entry field: "b" for bold, "i" for italics, "u" for underline", and "s" for strikethrough. The "link" button formats a link to a URL you specify and the  "image" button will let you insert a graphic into your comment..

One caution: Using either the "less than" (<) or "greater than" (>) symbols directly in your message will harm your message's formatting.  If your message requires either of those symbols, clicking the corresponding formatting button above the Subject entry field will insert the appropriate HTML code for that symbol into your message.


There are no comments yet

Leave a Comment




?
?

Powered by TalkBack